Water Programme

Proposol for water projects

7th October 2013

 St. Paul’s Sinoko and St. Mary’s Kipsing’ori Girl’s Secundary Schools.

 Bouwfotos 1 217x300 Waterprojecten Sinoko en Kipsingori

Background

 

The schools are in Trans-Nzoia east district Cherangany division. Both schools are Catholic sponsored under The Catholic Diocese of Kitale-Kaplamai parish.

 

St. Paul’s Sinoko sec. sch. is a mixed day and boarding school with student population of 505, 226 are boarding. It has long experience and persistent water problem mostly during dry and minimal rainy seasons. The school is forced to purchase water trough donkey transport at a cost of kshs 25000 every month.

 

St. Mary’s Kipsing’ori girl’s school is fairly an upcoming school with student population of 101. It is purely a girl’s day school with challennges of infrastructure i.e. administration block, classrooms, laboratory and kitchen. It has a small borehole that needs improvement to ensure sustainable water supply.

 

The Catholic Water Programme did water needs assessments in these schools and would like to intervene and solve the water problems through water well construction, pumping systems and roof catchment raim water harvesting.

 

Objectives:

1. To get clean water for domestic use in school

2. To reduce water cost and walking distances to water points.

3. To reduce the workload of school community and students in search of water.

4. To improve the quality of food preparation and hygiene in school.

5. To reduce water borne diseases.

6. To improver cleanliness and hygiene of children in school.

7. To create a conducive environment in school that increases enroiment and improved academic performance.

 

Main Activities:

1. Construction and Protection of a water well approximately 70 ft. deep.

2. Constructies of culvert for the protection of the water well sides.

3. Installation of electric water pumps.

4. Installation of overhead water tanks.

5. Water supply connections (pipelines).

6. Installation of water tanks and gutter systems for roof catchment rain water harvesting.

7. Constructions of water tap stands/collection points.

 

 

Bouwtek. Sinoko 217x300 Waterprojecten Sinoko en KipsingoriBouwtek. Kipsinggori 217x300 Waterprojecten Sinoko en Kipsingori

 

Dit zijn bouwtekeningen voor een waterproject.

Op de linkerfoto een ontwerp voor St. Mary’s Highschool in Kipsing’ori.

Op de rechterfoto een ontwerp voor St. Paul’s Highschool in Sinoko.

 

 

 

 

 

BENSINA CONTRACTORS LIMITED

                   P.O, Box 2920-30200, Kitale. Phone No.: 0710551154, 0734639468

   Email: sifunabenjamin@yahoo.com                                                                                                     

 

                                                                                                              Date:28th October 2013                             

 

 

 

 

1.     ST. PAUL’S SINOKO  SEC. SCHOOL

 

  1. A.    Water Well Project construction
Item Description Quantity Unit Unit Cost ksh Total Cost ksh
1 Digging 70 Ft.

800

56,000

2 Cement (bamburi) 30 bags

800

24,000

3 Water proof (pudlo) 30 kg

250

7,500

4 R-6mm iron bar 25 No.

200

5,000

5 Man hole cover 1 No.

2500

2,500

6 Weld mesh H/g 1 no

1200

1,200

7 Binding Wire m/g 15 Kg

150

2,250

8 Rope(heavy ) 50 m.

20

1,000

9 Ballast ¼’’ 7 Tones

2000

14,000

10 Sand (clean) 14 Tones

1200

16,800

11 Culvert Construction labour 25 No.

1000

25,000

12 Apron construction 1 No.

1000

1,000

13 Submersible pump Petrollo NKm4/4/float switch/Avs13A. 1 No.

65000

65,000

14 Transport l/s

10000

10,000

  Total Amount    

 

231,250

 

  1. B.     Installation of 5 water tanks and gutter systems for rain water harvesting and 1 overhead water supply tank
Item Description Quantity Unit Unit Cost ksh Total Cost ksh
1 Water tanks (10,000l) 1 No.

80000

80,000

2 Water tanks (5,000l) 5 No.

40000

200,000

3 Water tank stand 1 No.

30000

30,000

4 Cement 30 bags

800

24,000

5 Water proof (pudlo) 12 kg

250

3,000

6 Weld mesh H/g 8 no

1200

9,600

7 Binding Wire m/g 6 Kg

150

900

8 Ballast ½ ’’ 7 Tones

1500

10,500

9 Sand (clean) 10 Tones

1200

12,000

10 Gutters 120 No.

400

48,000

11 Gutter brackets 240 No.

20

4,800

12 Bondex 10 kg

250

2,500

13 Polythene sheet 20 metres

100

2,000

14 Construction labour l/s l/s

30000

30,000

15 Transport 4 trips

5000

20,000

  Total Amount    

 

477,300

  1. C.    Pipeline connection from the borehole to over head tank and to supply tanks
Item Description Quantity Unit Unit Cost ksh Total Cost ksh
1 ¾’’P.V.C Pipes C/C 120 No.

200

24,000

2 ¾ ’’ G.I Pipes C/A 20 No.

1200

24,000

3 ¾ ’’ Gate Valves 7 No.

1000

7,000

4 ¾’’G.I Sockets 10 no

40

400

5 ¾’’G.I Nipples 12 no

40

480

6 ¾’’G.I Back Nuts 10 No.

40

400

7 ¾’’G.I Long Nipples 10 pcs

100

1,000

8 ¾’’G.I Elbows 10 pcs

40

400

9 500g. Boss White 2 No.

200

400

10 ¾ ’’Pegler Taps 5 No.

1000

5,000

11 ¾ ’’Valve Sockets 14 No.

50

700

12 2’’P.V.C Pipes C/E 6 No.

1300

7,800

13 2’’ P.V.C Elbows 10 No.

200

2,000

14 Thread Seal Tapes 20 No.

40

800

15 Tangit Glue 250ml 6 No.

250

1,500

16 Hack Saw blades 4 No.

100

400

17 Transport 1 trip

5000

5,000

18 Plumbing Labour l/s l/s

15000

15,000

  Total Amount    

 

96,280

 

2.     ST. MARY’S KIPSINGORI GIRLS SEC SCHOOL.

 

  1. D.    Installation of a water pump in the water well, an over head supply water tank , 5 water tanks for roof catchment rain water harvesting/gutters and pipeline water supply
Item Description Quantity Unit Unit Cost ksh Total Cost ksh
1 Roto Water Tanks (10,000l) 1 No.

80000

80,000

2 Roto Water Tank (5,000l) 5 No

40000

200,000

3 Water Tank Stand & Piping 1 No.

30000

30,000

4 Cement-Bamburi 24 bags

800

19,200

5 Water Proof-Pudlo 12 kg

250

3,000

6 Weld Mesh H/G 6 no

1200

7,200

7 Binding Wire M/G 5 Kg

150

750

8 Ballast ½ ’’ 7 Tones

1500

10,500

9 Sand (Clean) 10 Tones

1200

12,000

10 Gutters 70 No.

400

28,000

11 Gutter Brackets 140 No.

20

2,800

12 Polythene Sheet 10 metres

100

1,000

13 ¾’’Pvc Pipes C/C 60 No.

200

12,000

14 ¾ ’’ G.I Pipes C/A 10 No.

1200

12,000

15 ¾ ’’ Gate Valves 5 No.

1000

5,000

16 ¾’’G.I Sockets 10 no

40

400

17 ¾’’G.I Nipples 8 no

40

320

18 ¾’’G.I Back Nuts 10 No.

40

400

19 ¾’’G.I Long Nipples 8 pcs

100

800

20 ¾’’G.I Elbows 10 pcs

40

400

21 ¾ ’’Pegler Taps 4 No.

1000

4,000

22 2’’P.V.C Pipes C/E 4 No.

1300

5,200

23 2’’ P.V.C Elbows 8 No.

200

1,600

24 Thread Seal Tapes 20 pcs

40

800

25 Tangit Glue 250ml 4 No.

250

1,000

26 Hack Saw blades 4

100

400

27 500g Boss White 1

200

200

28 ¾ ’’ Valve Sockets 12 No.

50

600

29 Submersible Pump Petrollo Nkm4/4/Float Switch/Avs13A. 1 no

65000

65,000

30 Construction Labour l/s l/s

20000

20,000

31 Transport 3 trips

5000

15,000

  Total Amount    

 

539,570

 

 

E. Contingencies                                                                                      Ksh 16,000

 

BUDGET SUMMARY

Total Project Cost = Item A. +  Item B. + Item C. + Item D. +  Item E

                                =( 231,250 + 477,300 + 96,280 + 539,570) = Ksh1,360,400.00

MAIN ACTIVITIES

St. Paul’s Sinoko Sec School

  • Digging and construction of borehole protected with culverts
  • Onsite construction of culverts
  • Installation of electric submersible pump to pump water to an overhead tank.
  • Installation of an overhead tank on top of a fabricated steel stand fixed to the ground. near to the borehole
  • Connection of 550 metre pipelines to water supply storage tanks and taps stations/points.
  • Installation of 5 rain water harvesting tanks and gutter systems in the dormitory and dining hall.

 

 

St. Mary’s Kipsingori Girls Sec. School

  • Installation of electric submersible pump to pump water to an overhead tank.
  • Installation of an overhead tank on top of a fabricated steel stand fixed to the ground near to the borehole.
  • Connection of 300 metre pipelines to water supply storage tanks and tap stations/points.
  • Installation of 5 rain water harvesting tanks and gutter systems in the classrooms and the office block.
  • Impoving existing borehole by inserting some culverts.

 

 

Note;                                                                                                                     

1.The total cost has increased due to increase of the number of tanks and  the distance from the bore holes hence the increase of the number of pipes

 

2. The account number for company is;

      Name:       BENSINA CONTRACTORS LIMITED

      Acc/No:    01 148 502 737 600

      Bank :       Co-operative Bank of Kenya

      Branch:    KITALE

 

 

Prepared by:  Mr. Benjamin Sifuna.